Retention and payment-stage calculator

Work out how much of a roof or façade contract to hold back as retention until the defects period ends, and what is still due after the advance you paid.

INR
%
INR
INR
Amount held back now (retention + deductions)
–
Payable to the contractor at completion
–

Illustrative estimate only — not an offer or quote.

Use this calculator at the completion stage of a roofing, waterproofing, cladding or painting job, when the contractor asks for the final bill. Enter the total contract value as agreed in writing (including GST if GST is charged), the retention percentage the contract allows you to hold back, any deductions agreed for items not done or done badly, and the advance and stage payments you have already made.

Formula: amount held back = contract value × retention % + agreed deductions. Payable at completion = contract value − amount held back − payments already made.

Worked example (illustrative): a ₹2,00,000 waterproofing contract plus 18% GST is ₹2,36,000. You paid a 30% advance (₹70,800) and 30% after the base coat (₹70,800), so ₹1,41,600 is already paid. With 10% retention (₹23,600) held until one monsoon has passed without leaks, the amount payable at completion is 2,36,000 − 23,600 − 1,41,600 = ₹70,800.

Limits: retention only works if it is written into the contract with the release condition (for example, a dated inspection after the first monsoon). The percentages here are examples, not a legal standard. See the contract and warranty checklist.